How do you set change classifications as major or minor?

Ayse Uras's picture
Ayse Uras asked on March 1, 2011 - 7:21pm | Replies (1).

Classifying changes as I/II is sometimes hard to agree even though we are guided by Mil HDBK 61, etc.

For instance, would you interpret a minor change on a customer approved spec always as I?
Or would you classify a major change on code as I prior to customer acceptance?

1 Answer

jptownsend's picture

Auras,

That is a question for the customer to answer. If they have signed off on the original change and now your changing it again. So they have to determine whether or not its a I or II level change.

For the level II changes same thing, what are the customers expectations. If you are going to UAT and made a code change, are they aware of the change. Whether you agree on it internally is irrelevant, its what the customer thinks and wants, whether they are internal or external.

Regards,

Joe